ESTIMATED ENVIRONMENTAL AND CONSTRUCTION SCHEDULE
REPORT DATE END Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
LOCATION AND IMPACT TYPE SUBMITTED DATE ‘17 ‘17 ‘17 ‘17 ‘18 ‘18 ‘18 ‘18 ‘19 ‘19 ‘19 ‘19 ‘20 ‘20 ‘20 ‘20 ‘21 ‘21 ‘21 ‘21
1 LOT 4.01 VOC AREA EXCAVATION RIR/RAW 5/13/16 4/1/18 April 1, 2018
2 BLDG 7 (MAIN CAMPUS) PILOT TEST RAW 12/29/16 6/1/18 June 1, 2018
3 SITEWIDE GROUNDWATER (VOCS) RIR 10/25/16 10/1/18 October 1, 2018
5 LNAPL SYSTEM Status Report/Work Plan 9/22/15 TBD Recovery by IR until state issues NFA
6 MAIN FACILITY AREA (MFA) REMEDIATION RIR/RAW 12/8/15 10/1/19 October 1, 2018
7 SOUTHERN FARM PARCEL NFA SIR/Addendum 10/23/15 7/1/17 July 1, 2017
8 CAMERON AREA LOTS 5/6 RAR RAR 4/3/14 7/1/18 July 1, 2018
9 LOT 7.04 PCB AOC RAW RIR/RAW 11/18/16 8/1/17 Aug 1, 2017
10 LOT 7.04 NON-LANDFILL FOUNDRY SAND RAR RAR 12/2/16 8/1/17 Aug 1, 2017
11 LOT 7.07 RAW RIR/RAW 5/9/16 4/1/18 April 1, 2018
12 LOT 7.06 RAW RIR/RAW 5/10/16 4/1/18 April 1, 2018
13 INVERSE PONDS RAR RAR/RTC 11/1/15 7/1/17 July 1, 2017
14 ABANDON FOUNDRY AREA WELLS Geosyntec letter to NJDEP 12/21/16 4/1/17 4/1/17
15 EASTERN FACILITY AREA (EFA) RAW RIR/RAW 5/10/16 7/1/19 July 1, 2019
16 BLDGS 2, 5, 6 RAW RAW 1/1/17 10/1/17 October 1, 2017
17 ABANDON ADDITIONAL WELLS Letter to NJDEP 1/1/17 7/1/20 July 1, 2020
CONSTRUCTION PHASE
1 DEMOLITION 7/1/16 7/15/17 July 15, 2017
2 FILL IMPORT BUILDING 3 4/1/17 11/1/17 November 1, 2017
3 FILL IMPORT BUILDING 2 10/1/18 10/1/19 October 1, 2019
4 FILL IMPORT BUILDING 1 12/1/19 1/1/20 January 1, 2020
5 CONSTRUCTION ENTRANCE 9/1/17 4/1/18 April 1, 2018
6 DUEL LEFT TURN LANE 12/15/18 1/1/19 January 1, 2019
7 P BURG PLAN APPROVAL 4/1/17 7/15/17 July 15, 2017
8 LOPATCON PLAN APPROVAL 4/1/17 7/15/17 July 15, 2017
9 UTILITIESPHASE I 8/1/17 5/1/18 May 1, 2018
10 UTILITIES PHASE II 7/1/18 12/15/18 December 15, 2018
11 SPINE RD LOPAT PHASE I 7/1/17 7/15/18 July 15, 2018
12 SPINE RD P BURG PHASE II 5/1/18 2/15/19 February 15, 2019
13 PHASE I LOPAT BUILDING 7 1/1/18 1/15/19 January 15, 2019
14 PHASE II -A BUILDING 2 1/1/18 1/15/19 January 15, 2019
15 PHASE II -B BUILDINGS 5-6 5/1/18 8/1/19 August 1, 2019
16 PHASE III - A BUILDING 3 10/1/17 11/1/18 November 1, 2018
17 PHASE III - B BUILDING 4 5/1/19 4/1/19 April 1, 2019
18 PHASE IV BUILDING1 4/1/19 4/1/20 April 1, 2020