ENTITLEMENT AND APPROVAL PROCESS - SCHEDULE
        The Following are the Approvals Process and/or schedule for I-78 Logistics Park, Phillipsburg and
        Lopatcong Townships, Warren County, New Jersey.


         Acquisition of all parcels               June 2016                             Stormwater Management Construction Plan  Complete
         Concept Plan Approval                    Complete
         Grading Plan                             Complete                              Erosion Sediment Control Plan            Complete
         Fill Import Plan                         Approved by both town and NJDEP
                                                                                        Public Water and Sewer Plans             Complete
         REDEVEL OPER S A GREEMENT                                                      Onsite Public Water and Sewer Plans      Complete
         Phillipsburg                             Approved                              Civivl Onsite Construction Plans         Complete
         Lopatcong                                Approved                              Public Works Will Serve Letters          Complete
         REDEVEL OPMENT PLAN                                                            Record Final Plat                        est. 8/2017 both towns
         Phillipsburg                             Approved
         Lopatcong                                Approved                              Site Cost Budget                         Complete

         GENERAL DEVEL OPMENT                                                           Site has been designated as a Redevelopment Zone by:
         PLAN                                                                           •   Both Townships
                                                                                            Grow NJ
                                                                                        •
         Phillipsburg                             Approved for 3.2 MSF                  •   Highlands
         Lopatcong                                Approved for 950,000 SF
                                                                                        The property has the following state designations
         Traffic Impact Study                     Complete                              •   UEZ Urban Enterprise Zone
         Preliminary Route 22 Left Turn Lane NJDOT  Approved                            •   EOZ Environmental Opportunity Zone
         Route 22 Turn Lane Engineering           Complete                              •   Highlands Exemption for Development
         Route 22 Turn Lane NJDOT Submission      Submitted February 2017               •   Grow NJ Grants
                                                                                        •   Long Term tax Exemption LTTE
         Geotechnical Reports
                                                                                        Property has over $3.250,000 in Redevelopment Area Bonds (RABs) in
         Demolition                               85% Complete will be done 7/2017
                                                                                        place to be used for infrastructure
         Community Input Meetings                 Complete
         Land Development Plan                    Complete
         Site Plan                                Complete
         Preliminary subdivision Plan             Complete

         FINAL SI TE PLAN  APPR O VAL             submitting to
         Lopatcong                                5/2017 est. approval 7/2017
         Phillipsburg                             5/2017 est. approval 7/2017

         Concept Stormwater Management Plan       Complete
         Landscaping Plan                         Complete