ENTITLEMENT AND APPROVAL PROCESS - SCHEDULE
The Following are the Approvals Process and/or schedule for I-78 Logistics Park, Phillipsburg and
Lopatcong Townships, Warren County, New Jersey.
Acquisition of all parcels June 2016 Stormwater Management Construction Plan Complete
Concept Plan Approval Complete
Grading Plan Complete Erosion Sediment Control Plan Complete
Fill Import Plan Approved by both town and NJDEP
Public Water and Sewer Plans Complete
REDEVEL OPER S A GREEMENT Onsite Public Water and Sewer Plans Complete
Phillipsburg Approved Civivl Onsite Construction Plans Complete
Lopatcong Approved Public Works Will Serve Letters Complete
REDEVEL OPMENT PLAN Record Final Plat est. 8/2017 both towns
Phillipsburg Approved
Lopatcong Approved Site Cost Budget Complete
GENERAL DEVEL OPMENT Site has been designated as a Redevelopment Zone by:
PLAN • Both Townships
Grow NJ
•
Phillipsburg Approved for 3.2 MSF • Highlands
Lopatcong Approved for 950,000 SF
The property has the following state designations
Traffic Impact Study Complete • UEZ Urban Enterprise Zone
Preliminary Route 22 Left Turn Lane NJDOT Approved • EOZ Environmental Opportunity Zone
Route 22 Turn Lane Engineering Complete • Highlands Exemption for Development
Route 22 Turn Lane NJDOT Submission Submitted February 2017 • Grow NJ Grants
• Long Term tax Exemption LTTE
Geotechnical Reports
Property has over $3.250,000 in Redevelopment Area Bonds (RABs) in
Demolition 85% Complete will be done 7/2017
place to be used for infrastructure
Community Input Meetings Complete
Land Development Plan Complete
Site Plan Complete
Preliminary subdivision Plan Complete
FINAL SI TE PLAN APPR O VAL submitting to
Lopatcong 5/2017 est. approval 7/2017
Phillipsburg 5/2017 est. approval 7/2017
Concept Stormwater Management Plan Complete
Landscaping Plan Complete
S I T E D E S CRI P T IO N 13